Construction projects on campus this summer

The following is a list of scheduled construction projects on campus this summer:

Construction of Augustana's newest building, the Peter J. Lindberg, M.D., Center for Health and Human Performance, will continue until the first week in September.

The Tredway Library stairs are being replaced and should be finished near the end of June.

Replacement of the Andreen staircase will start in mid-June 2021 and should be done near the end of July.  

Phase 1 of the Bergendoff interior renovation project starts May 24. This work is broken into two projects. The smaller portion of the work will be completed by Aug. 13  The second portion will be completed by Dec. 31.

Multiple roofing projects will take this summer as well at Bergendoff Hall of Fine Arts, the Olin Center and PepsiCo Rec Center.